Road Closure: Intersection of Jones Rd and Hoskyns Rd (Izone Business Park) closed from April 30

Road Closed: Road Closure

Intersection of Jones Rd and Hoskyns Rd (Izone Business Park) closed from April 30

Last updated
1 May 2018 4:40pm

From Monday 30 April, road closures will be in place at Jones Road/Hoskyns Road as part of the intersection upgrade works currently underway. The road closures will allow the new road pavement to be constructed in the shortest timeframe possible to minimise disruption.

Only a single leg of the intersection will be closed at a time in order to maintain short length detour routes.


Stages of closures will be:

  • Stage 1 closure – Hoskyns Road, north of the intersection
  • Stage 2 closure – Jones Road, west of the intersection
  • Stage 3 closure – Jones Road, east of the intersection

Detour routes

Signed detour routes will be via Links Road, using the Izone roundabouts and connecting side roads.

Duration

Each stage is expected to take one week to complete, however, work is weather dependent. Closures will remain in place until each stage is completed and will be removed before next closure takes effect. 

 

Stage 1 closure and detour - Scheduled start April 30 (One week)

Stage 2 closure and detour - Scheduled start May 14 (One week)

Stage 3 closure and detour - Scheduled start May 21 (One week)