Road Work: SH1 Timaru; Evans St, Theodosia St and King St - traffic delays overnight

Night Works: Road Work

SH1 Timaru; Evans St, Theodosia St and King St - traffic delays overnight

Last updated
17 Nov 2022 1:25pm

What: Night works: removing old surface and laying new asphalt

Where: SH1 Timaru - various locations

When: 7:00pm - 6:00am  

We’d like to advise motorists that we are starting work on multiple sections of asphalt surfacing replacement along SH1 in Timaru.

The work is being done at night to minimise disruption as we will need to reduce the road width to one lane of traffic each way at times. 

Traffic management on SH1 will consist of stages of two-lane diversion and single lane Stop/Go. The physical work will start at 8 pm but the traffic management will be set up earlier at 7 pm.

Two lanes will be open by 7 am each morning but there may still be congestion caused by temporary speed restrictions, uneven surfaces, and reduced lane widths.

Access for residents and local businesses will be available at all times but there will be disruption at intersections and on-street parking will be closed while we are working in the area. 

Additionally, upgrade works are being carried out during the daytime by Timaru District Council and others.

Road users should expect delays in this area next week, or avoid the worksite if they can. 

  • SH1 Theodosia St / Elizabeth St - Sophia St to Dee St - COMPLETED
  • SH1 Evans St, Showgrounds Hill - Jellicoe St to Grants Rd - three nights starting 20 November 2022
  • SH1 Evans St, Waimataitai - Grants Rd to Waimataitai St - five nights starting from 27 November 2022
  • SH1 King St, Redruth - Shaw St to Saltwater Creek - for one night (Dec 2022)
  • SH1 Theodosia St (Southbound Lane) - Wai Iti Rd to Sefton St E (SH78) - five nights (Feb2023) 
  • SH1 King St, Redruth - Otipu Rd to Shaw St - five nights (Feb 2023)

Additional day works being carried out by Timaru District Council and Alpine Energy:

  • SH1 Evans St - Waimataitai St to Ranui Ave Timaru Water, Wastewater and Stormwater upgrade project - through to December 2022 
  • SH1 Evans St/Grants Rd intersection - Commercial development service crossings, Access and Intersection Upgrade and Taitarakihi Culvert Replacement - starting Wednesday 23 November 2022 to November 2023 

Emergency services will have access at all times.

General Information

Safety is our number one priority. Safety is your responsibility too. Please follow the directions of our traffic management staff. Make sure you stay clear of the works, stay alert, and keep children and pets outside of work areas. 

Road works are a noisy and dirty work activity. We apologise for the noise and mess that we may cause while the works are underway. We appreciate your cooperation and patience.

For real-time Waka Kotahi NZ Transport Agency travel information visit: www.journeys.nzta.govt.nz

Phone: 0800 44 HIGHWAYS (0800 44 44 49)

And or follow https://www.nzta.govt.nz/contact-us/connect-with-us/

Thank you for your patience while we work in your area.