Roadworks: Riccarton Road Upgrade Project - Water and Sewer work at Riccarton Rd & Matipo St

Roadworks

Riccarton Road Upgrade Project - Water and Sewer work at Riccarton Rd & Matipo St

Riccarton Rd and Matipo St

Last updated
13 Jan 2020 1:35pm

Work will be carried out in stages at the intersection of Riccarton Rd & Matipo St. During all stages No Entry will be installed on Matipo St with no access to Riccarton Rd. Access to Riccarton Mall will be maintained.

Stage One (working in the middle east side): This layout is expected to be in place until 27 January 2020

  • Matipo St - one way southbound only between Riccarton Rd and Maxwell St (access to Riccarton Mall maintained)
  • Riccarton Rd - right-turning traffic into Matipo St will turn via the slip lane.

Matipo Riccarton Lane Shift

Stage Two (working in the middle west side):  

  • Matipo St - one way southbound only between Riccarton Rd and Maxwell St (access to Riccarton Mall maintained)

Stage Three (working southside of intersection): 

  • Matipo St - one way southbound only between Riccarton Rd and Maxwell St (access to Riccarton Mall maintained)

Stage Four (working northside of intersection):  

  • Matipo St - one way southbound only between Riccarton Rd and Maxwell St (access to Riccarton Mall maintained)