Scheduled Road Work: CSM2

Delays: Scheduled Road Work

CSM2

Works on Marshs Rd as part of CSM2
Stage 1
• Lane closure (one-way system) for 1 week – several concurrent activities:
o Completion of pavement remedials (NCRs 112 and 118) approx. 4 days – 2 days each lane
o Completion of median - 2 days
o Traffic pole install – pole 11 – 1 day
o SMA – tie-in at Shands – 1 day (after median)
o Commence EB tie-in works (Ch 860 to Ch 960)
Stage 2
• Lane closure (traffic signals) for 3 weeks
o Completion of EB tie-in works (Ch 860 to Ch 960)

Impacts
Capacity Reduction, Vehicle Lane(s) Closed, Turn Movement Closure, Cyclists Affected, Pedestrians Affected, Parking Removed, Detours In Place, Shoulder Closure
Start
14 Mar 2020 6:00am
End
12 Apr 2020 6:00pm
Last updated
26 Mar 2020 4:09pm
Company
McConnell Dowell Rebuild
TMP number
NZTA-CTOC-T62615
Reference
NZTA-CTOC-L322639