Resurfacing planned for State Highway 6 Whitby Road, Wakefield

NZ Transport Agency Waka Kotahi | 18 Nov 2026 2:41pm | Tasman, Nelson and Marlborough

The investment in state highways in the top of the South Island continues with pavement repairs and chipsealing on the way for State Highway 6 through Wakefield Village in Tasman.

Contractors will repair and chipseal a section of State Highway 6 Whitby Road, just under one kilometre long, from just west of Pitfure Road to just west of Edward Street, near the Wakefield Bakery.

Work is scheduled to begin on Sunday, 22 November and is scheduled to finish on Friday, 11 December – weather permitting.

The work is an important part of the region’s programmed road renewals.

The existing pavement on this section of State Highway 6 needs to be repaired. Repairing it now will provide an improved and safer road on a route that carries over 4,000 vehicles every day.

The work will be done in two stages. Pavement repairs will be underway from Sunday, 22 November, to Thursday, 3 December.

This will be followed by chipsealing, which will be completed between Monday, 7 December and Thursday, 10 December. As part of this work a special treatment of bitumen, chopped glass fibre and aggregate will be applied. This creates a strong, resilient, flexible water-resistant surface that will extend the life of the pavement without the need for a full road rebuild.

After all work is completed, temporary speed limits will remain in place until Friday, 18 December. This is to allow time for the chipseal to bed in, and for the sites to be swept and line-marked.

Impact on traffic

State Highway 6/Whitby Road will remain open throughout the project.

The work will be done at night, when traffic volumes are lower, under Stop/Go traffic management from 8 pm to 6 am, Sunday to Thursday nights.

Drivers should allow for delays of up to 10 minutes when travelling through the site.

There will also be noise, lighting, dust, and heavy machinery in operation at night. Contractors will do everything they can to keep disruption to a minimum for nearby residents and businesses.

This work is weather-dependent and schedules may change. With other work underway on the network, drivers are encouraged to plan ahead and check road conditions before they travel.

Works schedule

Pavement repairs:

  • Sunday, 22 November to Thursday, 3 December, 8 pm to 6 am, Sunday to Thursday nights
    • SH6 Whitby Road through Wakefield, from just west of Pitfure Road to just west of Edward Street near Wakefield Bakery.
    • Stop/Go traffic management with delays of up to 10 minutes. A reduced temporary speed limit will be in place 24/7 during this work.

Chipsealing:

  • Monday, 7 December to Thursday, 10 December, 8 pm to 6 am
    • SH6 Whitby Road through Wakefield, from just west of Pitfure Road to just west of Edward Street near Wakefield Bakery.
    • Stop/Go traffic management with delays of up to 10 minutes. A reduced temporary speed limit will be in place 24/7 during this work.
    • Access to and from Arrow Street via SH6 Whitby Road will be closed during working hours. Road users will need to detour via Edward Street.