SH1 Churton Park southbound offramp rebuild – day and overnight closures planned
NZ Transport Agency Waka Kotahi | 25 Nov 2026 9:46am | Wellington
Repairs and resurfacing are on the way for the southbound State Highway 1 offramp at Churton Park.
Daytime and nighttime closures will be needed for the work, which is scheduled to run from Sunday, 29 November until Wednesday, 2 December.
While this type of work is normally carried out during night closures, daytime closures are also required due to the nature of the work that needs to be done.
Because the pavement at the top of the offramp is weaker than the pavement in the lower sections, the road has to be excavated to a greater depth and extra layers of structural asphalt need to be laid to ensure the offramp’s pavement is properly rebuilt.
This means extra time is required to complete the job and it cannot be completed efficiently through night work alone. Two daytime shifts are needed to complete the rebuild, meaning the offramp will be closed during the day on Monday and Tuesday.
After the offramp reopens at 4:30 am on Wednesday, 2 December, to reduce traffic disruption, all remaining work will be carried out at night, when traffic volumes are lower.
Traffic impact
Drivers heading south on State Highway 1 to Churton Park and Glenside should be aware that the offramp will be closed continuously from 8 pm on Sunday, 29 November until 4:30 am on Wednesday, 2 December.
Drivers needing to access Churton Park and Glenside can detour by continuing to Ngauranga Gorge, exiting onto Centennial Highway, and then using the turning bay to rejoin State Highway 1 northbound. They can then exit at the Churton Park/Glenside northbound offramp (see map below). A turnaround detour at Johnsonville is not available for these works.
The detour will add approximately eight minutes to journey times. Drivers should allow extra time for their journeys and follow all signs and speed limits.
Why the work is needed
Motorway ramps connect the highway with local roads and need good grip and skid resistance. This offramp carries over 2,000 vehicles daily, so it is important that it is regularly maintained.
The repairs will create a safer, stronger road surface, one that will require fewer repairs in the future.
The work is weather-dependent and may be rescheduled at short notice. Please check the latest road conditions before travelling.
Work schedule and detour routes
- 8 pm Sunday, 29 November to 4:30 am Wednesday, 2 December (including all day Monday and Tuesday)
- SH1 Churton Park/Glenside southbound offramp CLOSED
- Detour: Continue south on State Highway 1 to Ngauranga Gorge and exit onto Centennial Highway. Use the turning bay to rejoin State Highway 1 northbound, then exit at the Churton Park/Glenside northbound offramp. The detour will add approximately 8 minutes to journey times